# Dependencies

What it is: Link tasks (e.g., finish-to-start) so sequencing and schedule impact are visible.

  1. Create the related tasks (e.g., Task A and Task B).

  2. Open Task B β†’ Dependencies β†’ select Task A and the relation type.
  3. Save and verify the connector on the timeline.

  4. Adjust Task A to see how Task B responds.
  • Good to know: Add main tasks first, then link. Avoid circular links (Aβ†’Bβ†’A).

# Common Questions

# Do linked tasks update when dates change?

Yes, downstream timing reflects the sequencing.